Did the Municipality of Lago Ranco, a lakeside town in southern Chile, overpay for a plot of land? The regional comptroller for Los Ríos says it did. In Final Special Investigation Report No. 245-2026, issued on October 1, 2026, the Contraloría Regional de Los Ríos reviewed the purchase of a 5,911 m² plot for 567,077,049 Chilean pesos. The town bought it in 2025 through direct contracting (“trato directo”), with no tender. According to the comptroller, the price was 424,177,357 pesos above the lowest of three commercial appraisals and 16.9 times the official tax valuation. The case matters because it combines the two classic red flags of public procurement in a single file: price and procedure.
The short answer. The comptroller concluded that the town justified neither the no-tender route nor the price, so it opened an administrative inquiry and sent the case to prosecutors. Those findings are in an official report. However, Mayor Miguel Meza Shwenke denies any overpricing and defends the plot’s historic value. Moreover, no court has ruled on any crime. Therefore, the administrative objection is documented, while any criminal liability remains unsupported.
What the town bought, and how
The property is Lot D 110 on Los Ángeles street in Lago Ranco, a municipality in the Los Ríos region. It covers 5,911 m², according to El Mostrador’s account of the comptroller’s objections. The town bought it in February 2025 through direct contracting, meaning without a public tender.
The stated purpose was a cultural project, which El Mostrador names as the Centro Cultural Ferrocarriles Madereros. Yet more than a year after the purchase, the land still had not been developed, the same outlet reported.
The inquiry did not start on the comptroller’s own initiative. Instead, it began with a citizen complaint to the Contraloría Regional de Los Ríos, as Diario Futrono reported when describing the origin of the file.
The price and the three appraisals
The municipality paid 567,077,049 pesos. To set that figure, it used the average of three commercial appraisals. However, the comptroller objected that nobody analyzed the “significant differences” among those three appraisals, according to Veredictum’s summary of the report.
For that reason, the comptroller measured the price against the lowest appraisal. The gap was 424,177,357 pesos. In addition, the amount paid equals 16.9 times the plot’s tax valuation. The mayor put that valuation at about 33 million pesos, which is consistent with the multiple the comptroller reported.
A budget line that doubled
Before the purchase, the relevant budget line rose from 285 million to 570 million pesos, according to Paislobo Prensa, which reproduced the report’s findings. In other words, the town nearly doubled the line, landing just above the final price. Mirada Sur noted that the comptroller tied this point to the planning rules in Law No. 18,695, Chile’s organic law on municipalities.
The comptroller’s objections
The report groups its concerns into four areas. Each one rests on a document or a legal rule, and regional and national outlets reported all of them.
Direct contracting without justification
The comptroller found that the town never justified direct contracting. As Mirada Sur reported, citing the laws the comptroller invoked, the report relied on Law No. 18,575 on the general principles of state administration. Likewise, the municipality could not show the grounds that authorized the purchase or a concrete need for the land.
Zoning limits that were ignored
The purchase contract ignored the plot’s legal restrictions. For example, the communal zoning plan classifies it as a ZE-3 zone, reserved for green space, sport and recreation. In that zone, buildings may cover at most 20% of the land. Furthermore, the plot carries a 30-meter public-utility easement. Finally, it reportedly lacks a direct sewer and water connection, according to Paislobo and Mirada Sur.
These facts matter for the price. Land that can barely be built on is, in principle, worth less than land with no limits. That is why the comptroller considered the restrictions relevant to whether the purchase was timely and sensible.
A project outside every plan
The cultural project did not appear among regional investments scheduled for 2026. Nor was it among the initiatives prioritized for 2027, El Mostrador reported. It was also missing from the communal development plan in force when the town decided to buy.
Appraisals the comptroller considered flawed
The town council backed the purchase unanimously, relying on the technical assessment of the municipal planning office (SECPLAN). However, the audit concluded that those appraisals were flawed and overvalued the land, according to Paislobo Prensa. The comptroller also rejected the town’s objections in full.
Table: the facts and their level of support
| Fact or claim | Who makes it | Date | Level of support |
|---|---|---|---|
| Purchase of Lot D 110 for CLP 567,077,049 by direct contracting | Contraloría Regional de Los Ríos, Report 245-2026 | October 1, 2026 | Proven |
| Price equal to 16.9 times the tax valuation | Contraloría Regional de Los Ríos | October 1, 2026 | Proven |
| CLP 424,177,357 above the lowest commercial appraisal | Contraloría Regional de Los Ríos | October 1, 2026 | Proven (as the report’s calculation) |
| That the gap is a real overcharge against the market | Comptroller asserts it; the mayor denies it | October and November 2026 | Documented, disputed |
| Direct contracting without valid grounds | Comptroller; the mayor defends the method | October 1 and November 12, 2026 | Documented, disputed |
| Administrative inquiry and referral to prosecutors | Contraloría Regional de Los Ríos | October 2026 | Proven |
| A crime or personal gain by any official | No authority has found it | None | Unsupported |
What the town paid versus the comptroller’s benchmarks
- Price paid
- CLP 567 M
- Above lowest appraisal
- CLP 424 M
- Times tax valuation
- 16.9
- Area
- 5,911 m²
- PurchaseDirect contract for CLP 567,077,049
- Report 245-2026Contraloría Regional de Los Ríos
- Inquiry and referralFile sent to prosecutors
- Mayor respondsDefends price, announces self-report
Source: Contraloría Regional de Los Ríos, as reported by El Mostrador, Paislobo Prensa and Mirada Sur (November 2026).
How Mayor Miguel Meza Shwenke responded
Lago Ranco’s mayor, Miguel Meza Shwenke, defended the purchase in a radio interview. According to Paislobo Prensa, which published his arguments on November 12, 2026, his defense rests on five points.
First, the no-tender route. Meza said the town wanted one specific plot, on the beach and next to the old pier, to recover local heritage. In his view, an open tender would have let sellers offer land with other features and locations.
Second, the price. The mayor disputed the comptroller’s use of the tax valuation as a yardstick. On that basis, he argued, land would cost about 5,900 pesos per square meter, a figure he called unrealistic. By contrast, the town paid roughly 95,000 pesos per square meter.
Third, comparable sales. Meza cited deals recorded at the property registry for plots farther from the beach. He mentioned 125 million pesos for 1,400 m², 145 million for 1,200 m², and 165 million for just over 1,200 m². None of those sales is verified in the report, so they remain the mayor’s figures.
Fourth, the appraisals. The mayor said the town hired registered outside firms and that the offer fell within the market average. Fifth, the nature of the report. Meza argued that it points to administrative issues, not intent. He also complained of attacks on his reputation on social media.
Finally, he announced a voluntary self-report to prosecutors. He said he would hand over his personal, banking and electronic-device records. “I have absolutely nothing to hide,” he said, according to El Mostrador. As of November 12, the self-report was only an announcement, with no filing date reported.
What the response leaves out
The mayor’s defense focuses on heritage value and price per square meter. However, Paislobo Prensa noted that he did not address the ZE-3 zoning, the 20% building cap, the 30-meter easement or the missing sewer connection. Those are precisely the limits that lower a plot’s value.
What happens next
The case now moves on two separate tracks. The first is administrative. The comptroller’s external control unit will run an inquiry (“sumario”) to establish the liability of officials whose actions or omissions allowed the purchase. In addition, the town had ten business days to show that it formally informed the council of the report.
The second track is criminal. The comptroller sent the file to the Regional Prosecutor’s Office of Los Ríos. However, none of the sources consulted reports any formal charges or private criminal complaint. As a result, as of November 19, 2026, nobody stands accused in this case.
One point deserves emphasis. For now, the inquiry does not target any person named in the sources. The mayor appears as the public defender of the purchase, not as an identified subject of the inquiry.
So, what is proven?
- Proven: the Municipality of Lago Ranco bought a 5,911 m² plot by direct contracting in 2025 for CLP 567,077,049, according to Final Report No. 245-2026 of the Contraloría Regional de Los Ríos.
- Proven: the comptroller calculated that the price was CLP 424,177,357 above the lowest appraisal and 16.9 times the tax valuation.
- Proven: the comptroller ordered an administrative inquiry and referred the file to the Regional Prosecutor’s Office.
- Documented, disputed: that the town overpaid against the market and that direct contracting was unjustified. The comptroller says so; Mayor Meza rejects it with comparable sales and heritage arguments.
- Unsupported: that any official committed a crime or gained personally. No authority has established that.
Frequently asked questions (FAQ)
How much did Lago Ranco pay for the land?
It paid 567,077,049 Chilean pesos for a 5,911 m² plot, Lot D 110 on Los Ángeles street. The purchase took place in 2025 through direct contracting, without a tender. The figure appears in Final Special Investigation Report No. 245-2026 of the Contraloría Regional de Los Ríos, issued on October 1, 2026.
Was the Lago Ranco land purchase overpriced?
The comptroller says yes, but the mayor denies it. The report calculates that the price was 424,177,357 pesos above the lowest of three appraisals and 16.9 times the tax valuation. Mayor Miguel Meza Shwenke, however, says the town paid about 95,000 pesos per square meter, below nearby plots. Therefore, the claim is documented but disputed.
Why did the comptroller object to direct contracting?
Because the town never explained why it skipped a tender. According to the report, it also failed to show a concrete need for the land or to weigh its zoning limits. The mayor replies that he sought one unique plot by the old pier and that a tender would have drawn different land. The comptroller rejected those arguments.
Is the mayor of Lago Ranco facing charges?
No. As of November 19, 2026, no source reports formal charges against the mayor or any other official. The comptroller ordered an administrative inquiry and sent the file to the Regional Prosecutor’s Office. Meanwhile, the mayor announced a self-report so prosecutors can review his accounts. So far, no one has established a crime.
What restrictions apply to the plot?
Several, according to the comptroller. The zoning plan classifies it as a ZE-3 zone for green space, sport and recreation, with buildings capped at 20% of the land. It also carries a 30-meter public-utility easement and reportedly lacks a direct sewer connection. The purchase contract did not account for those limits, the report says.
What happens to the case now?
It moves on two tracks. On one side, the comptroller’s inquiry will establish officials’ administrative liability. On the other, the Regional Prosecutor’s Office of Los Ríos received the file and will decide whether to investigate any crime. Meanwhile, the land remained undeveloped more than a year after the purchase, according to El Mostrador.
Sources consulted
- El Mostrador: Lago Ranco: los reparos de Contraloría a una compra de $567 millones (November 18, 2026)
- Paislobo Prensa: Contraloría envía a Fiscalía polémica compra del municipio de Lago Ranco (November 11, 2026)
- Paislobo Prensa: Lago Ranco: Alcalde responde a Contraloría por sobreprecio de $424 millones (November 12, 2026)
- Mirada Sur: Alcalde de Lago Ranco defiende compra de terreno observada por Contraloría (November 12, 2026)
- Veredictum: Contraloría detecta compra de terreno 16,9 veces avalúo (November 10, 2026)
- Diario Futrono: Tras denuncia ciudadana Contraloría instruye sumario por compra de terreno con sobreprecio en Lago Ranco (November 11, 2026)
Legal note: This article reports documented facts and allegations attributed to their authors. Mentioning an allegation does not imply that it is true, and the responses of the person concerned are included in each case. Auditoría Abierta offers Mayor Miguel Meza Shwenke and the Municipality of Lago Ranco space to respond and will update this article with any new development. Information verified as of November 19, 2026.

Investigative Journalist and Political Analyst
Eri Miranda Loya is an investigative journalist specializing in public affairs coverage, power structure analysis, and institutional oversight in Latin America. His journalistic work stands out for the intensive use of transparency techniques, freedom of information access, and documentary cross-referencing, aimed at untangling the regulatory and financial webs of the political class.
At Auditoría Abierta, he is part of the investigative team focused on accurately documenting cases of opacity, legislative controversies, and accountability. His approach prioritizes informational sobriety, respect for due process, and the rigorous use of primary sources to provide citizens with bias-free journalism grounded in verifiable facts.